Timeline

Development has started at The Hideaway Luxury Villa & Spa in Krabi, Thailand.

The work is expected to complete in October 2023

This is our projected construction timeline for a villa.

A Villa Project Timeline

Month #1

  • Preparation
    • Design development and construction drawings.
    • Site preparation, demolition, paperwork and site work.

Month #2 – 3

  • Base
    • Concrete foundations & slab.

Month #3 – 4

  • Frame
    • Wall frame and roof trusses.

Month #4 – 5

  • Lock Up
    • Roofing, brickworks, doors and windows, tiling and rough-in.

Month # 5 – 6

  • Fixing
    • Interiors, cabinets, baths and sinks.

Month #6 – 7

  • Completion
    • Painting and Fix-offs
      Handover & documents.

Month #7 – 8

  • Settlement
    • Get the keys.

 

Preparation

  • Design development and construction drawings.
  • Site preparation, demolition, paperwork and site work.
Month #1
Month #2 - 3

Base

Concrete foundations & slab.

Frame

Wall frame and roof trusses.

Month #3 - 4
Month #4 -5

Lock Up

Roofing, brickworks, doors and windows, tiling and rough-in.

Fixing

Interiors, cabinets, baths and sinks.

Month #5 - 6
Month #6 - 7

Completion

  • Painting and Fix-offs
  • Handover & documents.

Settlement

Get the keys.

Month #7 - 8

Note: Times are estimated and subject to change.